2nd Street Streetscape Improvement Project 2025

Update as of 9/30/2025

The 2nd Street Streetscape Project is progressing well with more than 30% complete with final completion expected before Labor Day in 2026.

Phase 1, between Sanford Avenue to Palmetto Avenue, is 80% complete

Phase 2, between Palmetto Avenue to Magnolia Avenue, has begun with completion expected by the end of November.


Phase 3, between Magnolia Avenue to Park Avenue, is expected to begin early November and end by February.


Phase 4, between Park Avenue to Oak Avenue is expected to begin in January and end by April.
Final cleanup and presentation to our City residents is expected by the end of May

Update as of 9/24/2025

The 2nd Street Streetscape Project is progressing. There have been some rain delays and as with old infrastructure, utilities issues. 2nd Street between Sanford Avenue and Palmetto is open and we are waiting on the landscaping, light poles and electrical to finish up. The anticipated time for the concrete and brick work to be completed between Magnolia Avenue and Palmetto Avenue in Mid-November. The next phase will entail the intersection at Magnolia to Park Avenue which will take approximately 3 months. All of this is tentative barring there are no issues.

 

Update as June 2025

The City of Sanford will begin the 2nd Street Streetscape Project in June. This project, spanning Sanford Avenue to Oak Avenue, involves making the roads ADA-compliant, relaying bricks, increasing the availability of parallel parking spaces, installing new light fixtures, and enhancing electrical outlet options for vendors and food trucks. The work will be carried out in phases to minimize traffic disruptions. For more information you may contact the Street Division for sidewalk and curb reconstruction at 407-688-5000 Option #5

Powered By EmbedPress

2nd Street Streetscape Improvements City of Sanford

Jeff Davis, Project Manager for the Public Works Street Division, has shared exciting news about the upcoming 2nd Street Streetscape project, scheduled to begin in June 2025. This transformative project aims to revitalize the area with essential road improvements. The plan includes adding more parking spaces to make life more convenient for residents, installing additional electrical outlets, relaying brickwork for a polished look, and upgrading the area with new lighting fixtures.

Previous City of Sanford Receives FMCA Certificate of Excellence in Government Communications

300 N Park Ave
Sanford FL, 32771

Mon – Thur:  7:00 am – 5:30 pm

Fri:  8:00 am – 1:00 pm

Stay Connected

City of Sanford, FL | The Friendly City