Road Resurfacing and Reclamation Project Updates

The City of Sanford has contracted with Asphalt Paving Systems, Inc. for upcoming roadway reclamation and paving work to improve local infrastructure.

Project Schedule & Duration

  • Project Window: Weeks of October 12 and October 26

  • Location: Designated neighborhood roadways

FULL DEPTH - M O.jpg: A technical paving plan graphic featuring a data table, an aerial map, and a callout box. Table: Outlines four street segments (Holly Avenue, Maple Avenue, Cedar Avenue, and 22nd Street) between 22nd Street, 18th Street, French Avenue, and Cedar Avenue, specifying paving type "FD - 2.0 -SP12.5" and yardage measurements. Map: An aerial view of a residential grid highlighting road sections marked in green and red lines along Cedar Ave, Holly Ave, Maple Ave, W 18th St, W 20th St, and W 22nd St. Callout Box: Text on the right reads "ROADS FOR FULL DEPTH WILL RECEIVE 2 INCHES OF SP12.5 ASPHALT".
A street map diagram showing a residential neighborhood grid with specific road segments highlighted in bright yellow. The yellow highlights mark sections of South Lake Avenue, Cedar Avenue, South Holly Avenue, and South Maple Avenue running north-south between W 22nd Street, W 24th Street, W 24th Place, and W 25th Street. Nearby landmarks labeled on the map include Pinehurst Park Playground, Child Care Center, Guns N Comics, Hungry Howie's Pizza & Subs, and Oakport Dental.

What to Expect During Construction

  • Traffic & Access: Minor delays and inconveniences should be expected. During working hours, limited access will be maintained and coordinated onsite by work crews and traffic control personnel.

  • Full Access: Residents will have full access to resurfaced roads during non-working hours.

  • Milling & Elevation Drops: Roadways will be treated and reshaped before a new lift of asphalt is applied. Expect elevation drops of up to 2 inches—please travel slowly and cautiously through work zones.

  • Paving Timeline: Please allow up to 7 days between roadway treatment and the installation of the final asphalt overlay.

Resident Action Required

To ensure work can be performed safely and efficiently, vehicles must be removed from the roadway:

  • No-Parking Window: 7:00 AM to 7:00 PM on the scheduled day of application.

  • Restrictions: Absolutely no vehicles, boats, trailers, or debris may be left in the roadway during these hours. Vehicles left in the right-of-way will be towed at the owner’s expense.